University of Illinois at Urbana-Champaign, McKinley Health Center

Urbana-Champaign, IL

UIUC, McKinley Health Center, exterior

Overview

McKinley Health Center is an outpatient healthcare facility serving the UIUC community, hosting more than 100,000 visits a year. Built in 1926, the facility was originally a 42,700-square-foot hospital; several additions and renovations have since occurred, resulting in a roughly H-shaped facility with two main wings (A and B).

The project replaced about 150 fan coil units that had originally been installed in 1986 and were beyond their useful service life. Collaborating firms on the project included Reifsteck Reid & Company (architectural) and Carnow Conibear & Associates (environmental services).

Fan Coil Unit Replacements, Engineering Design

The scope for this large project included demolishing existing fan coil units, installing new units, reworking piping as needed, adding insulation, and providing electrical work and incidental ductwork. To prevent disruption to building services, work was divided into two major phases: an initial phase involving about 100 existing fan-coil units (FCUs) in Buildings A and B, and a second phase involving about 40 FCUs in Building A. Night shift work was also required to ensure that healthcare services could continue.

As part of the second phase, some basement renovations in Building A were included. These comprised controls upgrades for 11 convectors, one cabinet unit heater, and nine reheat coils, and replacement of one FCU. Controls for five reheat coils in the basement medical records department were also upgraded, as were controls for one coil in a pharmacy storage area.

New FCUs were provided with new control valves with DDC controls, necessitating replacement of prior controls and a new tie-in to the building automation system. A new automation server (main head-end controller) was also installed and programmed. As needed, programming for affected air-handling units was also adjusted.

Chilled and hot water isolation valves were added in locations coordinated with the university’s maintenance team, and fire protection sprinklers were removed then reinstalled in order to accommodate the mechanical work.

Electrical connections to fan-coil units were demolished and new connections provided, as well as power for new DDC panels.

Access to the existing chilled water and hot water piping was generally through the ceiling space below the FCUs, and ceiling repairs were part of the architectural scope, as well as other necessary finish repairs. The team also included an environmental consultant to ensure safety associated with asbestos and lead.

View More Projects

Interested in learning more about how GBA can assist with your facility objectives? Our portfolio is a great place to start. 

Skyscraper board room

430 N. Michigan (Realtor Building)

A large-scale vertical expansion called on GBA's analytical, design, and commissioning skills.

Hallway with rehab equipment

Shirley Ryan AbilityLab, Pediatric & DayRehab Center

This outpatient center serves children and adults; GBA provided engineering design services for the adaptive reuse project.

Exterior of Todd Building, University of Kentucky

University of Kentucky, Lee T. Todd, Jr. Building

An ASHRAE Level 1 audit,  retro-commissioning, and a lab ventilation assessment improved sustainability.