University of Chicago, Ricketts Biocontainment Lab

Lemont, IL

Exterior of the Ricketts Biocontainment Laboratory on the campus of Argonne National Laboratory

Overview

The $15.3 million Howard T. Ricketts Regional Biocontainment Laboratory is one of nine new regional facilities supporting research for the detection, prevention, and elimination of diseases such as anthrax, hemorrhagic fever, influenza, and plague. The 50,000-square-foot building contains BSL-2 and BSL-3 laboratories, BSL-2 and BSL-3 vivariums, and required support spaces. The University of Chicago received a grant from the National Institute of Allergy and Infectious Diseases (NIAID) to construct the building on the campus of the Argonne National Laboratory.

Commissioning, Re-commissioning, and Validation

The commissioning plan and scope of services were based on the National Institutes of Health (NIH) Commissioning Guidelines.

  • Mechanical systems commissioned included supply air handling systems, laboratory and vivarium exhaust systems, cage wash exhaust systems, chilled water system (including one chiller and cooling tower), heating hot water system, steam and condensate systems, run-around heat recovery system, clean steam humidification system, and the building automation system.
  • Plumbing and lab gas systems commissioned included the domestic hot water system, two independent lab compressed air systems, and the lab vacuum system.
  • Electrical systems commissioned included the electrical distribution system, emergency power system (with one emergency generator), paging system, lighting controls system, UPS system, and security.

Design-phase services included schematic design, design development and construction documents design review, preparation of the commissioning plan (including development of prefunctional checklists and functional performance testing procedures), and preparation of commissioning specifications for incorporation into bidding documents.

Construction-phase services included periodic site observations, review of key shop drawings, and attendance at periodic construction meetings.

Acceptance-phase commissioning services included spot checking of start-up and balancing, functional performance testing, and compilation of design operation and maintenance information. Opposite-season testing was performed. Extensive testing of all failure modes was performed, resulting in adjustments to ensure that the containment of the BSL-3 and BSL-3 vivariums is maintained.

GBA performed re-commissioning and validation work several years after the lab opened, again under NIH guidelines.

View More Projects

Interested in learning more about how GBA can assist with your facility objectives? Our portfolio is a great place to start. 

Skyscraper board room

430 N. Michigan (Realtor Building)

A large-scale vertical expansion called on GBA's analytical, design, and commissioning skills.

Hallway with rehab equipment

Shirley Ryan AbilityLab, Pediatric & DayRehab Center

This outpatient center serves children and adults; GBA provided engineering design services for the adaptive reuse project.

Exterior of Todd Building, University of Kentucky

University of Kentucky, Lee T. Todd, Jr. Building

An ASHRAE Level 1 audit,  retro-commissioning, and a lab ventilation assessment improved sustainability.