Overview

This work (done with an electrical engineering partner firm) created a new Grade C (ISO 7) cleanroom in an existing pharmaceutical manufacturing facility.

Line Formulation Project, Design

  • The design incorporated modular construction, which was designed, tested, and certified to ISO cleanroom standards.
  • Process work included two new formulation tanks, a mixing tank, a filtrate tank, and process piping skids.
  • Critical utilities included water for injection, pure steam, clean compressed air, and process chilled water for tank jackets.

View More Projects

Interested in learning more about how GBA can assist with your facility objectives? Our portfolio is a great place to start. 

Skyscraper board room

430 N. Michigan (Realtor Building)

A large-scale vertical expansion called on GBA's analytical, design, and commissioning skills.

Hallway with rehab equipment

Shirley Ryan AbilityLab, Pediatric & DayRehab Center

This outpatient center serves children and adults; GBA provided engineering design services for the adaptive reuse project.

Exterior of Todd Building, University of Kentucky

University of Kentucky, Lee T. Todd, Jr. Building

An ASHRAE Level 1 audit,  retro-commissioning, and a lab ventilation assessment improved sustainability.