Hyatt Regency Aruba Resort Spa and Casino

Palm Beach, Aruba

Hyatt Regency Aruba, exterior

Overview

This facility is a 424,823-square-foot, 360-room hotel. Although Aruba is surrounded by an ocean, the cost of potable water on the island is exceedingly high and is provided by several large membrane and thermal desalination plants. The purpose of this project was to recover as much as 6 million gallons of water annually from the hotel’s laundry. A system was designed to recover laundry waste water and air-conditioning condensate for use in cooling tower makeup. The project resulted in an annual savings of $46,960 and paid for itself in 2.7 years.

Awards

ASHRAE, Society-Level Technology Award (first place), 2003

ASHRAE, Region VI Technology Award (first place), 2002

ASHRAE Illinois, Excellence in Engineering Award, 2001

Laundry Water Recovery System

This project’s recovery system recovers a far higher percentage of water than systems that are commercially available – over 90% of the water is recovered. GBA determined that most of 6 million gallons of water per year could be recovered using commercially available technology that was familiar to the operators of the hotel. A storage tank of about 4,000 gallons was required to match the water use of the towers — which is nearly constant — with the laundry’s discharges of hundreds of gallons in short bursts. In addition, cooling coil condensate could be recovered from nearby systems for use in the recovery system.

Equipment and materials were pre-purchased in the United States and shipped to the site. System equipment included:

  • A trash pump, which transfers laundry waste water to a storage tank
  • A 177-micron separator located upstream of the tank, which filters the waste water
  • A 5-micron multi-media filter recirculating to the tank, to provide final filtration

A chemical treatment system includes biocide, an anti-foam agent, and pH control. Recovered makeup water is metered for diagnostics and documentation. Alarms and controls provide information on tank level, filter backwash, pump start-stop, and chemicals.

Construction was managed entirely by the hotel. Commissioning and training were provided by the equipment vendors.

View More Projects

Interested in learning more about how GBA can assist with your facility objectives? Our portfolio is a great place to start. 

Skyscraper board room

430 N. Michigan (Realtor Building)

A large-scale vertical expansion called on GBA's analytical, design, and commissioning skills.

Hallway with rehab equipment

Shirley Ryan AbilityLab, Pediatric & DayRehab Center

This outpatient center serves children and adults; GBA provided engineering design services for the adaptive reuse project.

Exterior of Todd Building, University of Kentucky

University of Kentucky, Lee T. Todd, Jr. Building

An ASHRAE Level 1 audit,  retro-commissioning, and a lab ventilation assessment improved sustainability.