University of Illinois at Urbana-Champaign, CERL

Urbana-Champaign, IL

UIUC CERL, exterior

Overview

CERL, the U.S. Army Construction Engineering Research Laboratory, opened in 1969. CERL develops and tests technologies for the U.S. Department of Defense. CERL and the University of Illinois collaborate under an Educational Partnership Agreement.

These two projects consisted of installing a new code-compliant fire protection system in Building 2 and upgrading the central heating and building heating systems for the CERL campus complex.

CERL Fire Suppression and Heating System Upgrades, Design

The CERL campus consists of four facilities: Main Buildings 1, 2, and 3; and the TESS (Triaxial Earthquake and Shock Simulator) Building. G/BA performed two separate engineering design projects to upgrade CERL.

The Heating System Upgrades project consisted of replacing outdated existing equipment in the CERL utility building with new, higher efficiency equipment, helping address a federal mandate to reduce annual energy usage by 3%.

  • Equipment was sized to provide adequate capacity to serve existing and future buildings and provide N+1 redundancy. One new condensing boiler was provided, and two existing boilers were retained. The oldest existing fire tube boiler was earmarked for demolition but temporarily kept in service as a backup. Additional upgrades are anticipated.
  • All boilers were integrated into an automated sequencing control system, improving system performance and efficiency.
  • New pumps were installed to meet the campus heating system’s flow and pressure requirements. These were integrated with existing hot water pumps serving Buildings 1 and 2, which may be replaced at a later date.
  • The project included new piping, valves, floor drains, and associated electrical service.

The Building 2 Fire Suppression Systems project provided new fire suppression systems to Main Building 2, including wet and dry pre-action sprinkler systems according to NFPA 13. The project included the installation of a new 1,000-gpm, diesel-engine-driven packaged fire pump per NFPA 20, installed in an exterior enclosure to provide fire suppression to the entire CERL campus.

  • A new water service was provided from the city main on the south side of the site.
  • Future fire protection connections were provided for the proposed infill building, Main Building 1, Main Building 3, and the TESS Building.
  • Architectural scope of the project (by a subconsultant) included finish repairs, ceiling replacements, and soffits in areas affected by new sprinkler piping.
  • Civil scope of the project (by a subconsultant) included fire pump enclosure location coordination, foundation design, underground utility coordination, road and signaling modifications, and landscaping restoration.

View More Projects

Interested in learning more about how GBA can assist with your facility objectives? Our portfolio is a great place to start. 

Skyscraper board room

430 N. Michigan (Realtor Building)

A large-scale vertical expansion called on GBA's analytical, design, and commissioning skills.

Hallway with rehab equipment

Shirley Ryan AbilityLab, Pediatric & DayRehab Center

This outpatient center serves children and adults; GBA provided engineering design services for the adaptive reuse project.

Exterior of Todd Building, University of Kentucky

University of Kentucky, Lee T. Todd, Jr. Building

An ASHRAE Level 1 audit,  retro-commissioning, and a lab ventilation assessment improved sustainability.