Advocate Lutheran General Hospital

Park Ridge, IL

Advocate Lutheran General Hospital campus view, Park Ridge, IL.

Overview

GBA performed a second phase of retro-commissioning at the 1,672,758-square-foot facility that prioritized the chilled water system, newer bed tower AHUs, and operating room setbacks. A total of 934,000 kWh/yr of savings were identified in this project, representing annual cost savings of nearly $32,000.

Retro-Commissioning

Advocate Lutheran General Hospital consists of a new bed tower, main hospital building, Children’s Hospital, and Level I trauma center. GBA’s retro-commissioning effort included the following:

  • GBA provided an updated single-line drawing showing the entire chilled water system, including all 12 tertiary bridge loops and connected AHUs.
  • An updated sequence of operations was created for the chiller staging between the site’s two plants: one with four 750-ton Carrier chillers and one with two 700-ton York machines.
  • The RCx team identified 41 retro-commissioning measures associated with the chilled water system and tertiary bridge loops, including sequence of operation revisions; installation of VFDs; removal of bridge tenders; AHU control modifications; and removal of pumps.
  • Before RCx, operations required manual staging of the main plant’s secondary chilled water pumps, based on observation of existing dP station pressures. GBA recommended a strategy, and new sequence logic, to provide automatic staging.
  • GBA found that the two transfer pumps meant to send water from the smaller surgery chiller plant into the mains were under-sized. The pumps could not overcome the pressure in the system unless both of them were running. The RCx team recommended using an existing standby pump—which was a backup to the surgery chiller’s primary pumps—as a transfer pump. This allowed the facility to save energy by running the larger standby pump rather than running both transfer pumps simultaneously.
  • In addition to recommending improvements for the chilled water system, GBA was able to identify 12 issues with the current operating rooms and their associated AHUs.

View More Projects

Interested in learning more about how GBA can assist with your facility objectives? Our portfolio is a great place to start. 

Skyscraper board room

430 N. Michigan (Realtor Building)

A large-scale vertical expansion called on GBA's analytical, design, and commissioning skills.

Hallway with rehab equipment

Shirley Ryan AbilityLab, Pediatric & DayRehab Center

This outpatient center serves children and adults; GBA provided engineering design services for the adaptive reuse project.

Exterior of Todd Building, University of Kentucky

University of Kentucky, Lee T. Todd, Jr. Building

An ASHRAE Level 1 audit,  retro-commissioning, and a lab ventilation assessment improved sustainability.