Advocate Good Shepherd Hospital, AHUs

Barrington, IL

Advocate Good Shepherd Hospital, exterior

Overview

This $510,000 project replaced the existing, outdated, suspended 13,000-cfm air handling unit in the basement mechanical room of an existing hospital outpatient building constructed in 1983. Two AHUs that serve the operating suite were also upgraded.

Air Handling Unit Replacement and Commissioning

A new AHU was set in place in an adjacent mechanical room storage space and made completely operational before the shutdown and demolition of the existing AHU. The return fan was replaced during one night-time shutdown. The new AHU design was carefully planned to allow AHU sections to move through existing corridors and doorways, with subsequent reassembly in the basement mechanical room.

A new multiple supply fan array design provided a small AHU footprint and increased operational reliability. New temperature controls included airflow measuring stations with fan tracking to ensure indoor air quality (minimum outside air intake) and building pressurization capability.

Project work also included upgrades to two AHUs serving the operating suite from 100% outdoor air operation to recirculated air for energy conservation. The safe impact of the conversion to recirculation was analyzed and confirmed.

GBA commissioned both the primary AHU replacement and the operating suite AHU upgrade.

View More Projects

Interested in learning more about how GBA can assist with your facility objectives? Our portfolio is a great place to start. 

Skyscraper board room

430 N. Michigan (Realtor Building)

A large-scale vertical expansion called on GBA's analytical, design, and commissioning skills.

Hallway with rehab equipment

Shirley Ryan AbilityLab, Pediatric & DayRehab Center

This outpatient center serves children and adults; GBA provided engineering design services for the adaptive reuse project.

Exterior of Todd Building, University of Kentucky

University of Kentucky, Lee T. Todd, Jr. Building

An ASHRAE Level 1 audit,  retro-commissioning, and a lab ventilation assessment improved sustainability.