Advocate Christ Medical Center, Pharmacy Expansion

Oak Lawn, IL

Advocate Christ Medical Center, Oak Lawn, IL.

Overview

Christ Medical Center is a south metro, 750-bed, 579,340-square-foot hospital. It is a full-service facility built in many phases since its original construction in 1958. GBA provided engineering design for the renovation and expansion of a 1972-era, basement-level pharmacy with complete replacement of an outdated, dual-duct HVAC system. Continuous 24/7 occupancy was maintained during construction.

Pharmacy Expansion and HVAC Replacement, Design

The scope included expansion and upgrades to the entire 14,000-square-foot basement-level pharmacy space, including new sterile solutions rooms meeting USP 797 requirements. An outdated constant volume, 100% outdoor air dual-duct HVAC system required capacity expansion and equipment replacement, including replacement of the central AHU and new distribution throughout the occupied space. Pharmacy operations had to be maintained during construction, requiring a multi-phase plan and HVAC renovation schemes that would ensure ventilation and minimize service interruptions. GBA provided full mechanical design services.

  • The 40,000-cfm central AHU was replaced with a new, built-in-place AHU in the same location (second-floor mechanical room). To maintain continued ventilation, a temporary trailer-mounted air-handling unit with added air filtration and temporary piping services was installed outside.
  • Multiple exhaust fans were replaced, and major duct revisions were made, to convert the 100% outdoor air system to a recirculated air system. Airflow controls were added to convert the fans to a multiple return fan arrangement.
  • Existing dual-duct supply mains routed throughout the ceiling spaces were retained but converted from a cold duct/hot duct arrangement to dual cold ducts, repurposed to obtain increased airflow capacity. Return duct mains were both retained and augmented to obtain increased return airflow.
  • Dual-duct boxes were replaced with new VAV boxes with hot water reheat in a carefully phased sequence to ensure continued ventilation safety and comfort.
  • A new hot water reheat piping system was installed in a carefully phased sequence to allow a piecemeal dual-duct box replacement scheme.
  • Building areas outside the project scope were accommodated by retaining existing dual-duct boxes and installing central airflow controls and heating coils, which re-served such spaces with a continued hot-duct/cold-duct arrangement.
  • New cleanroom-type ventilation was installed to service the new sterile solutions rooms.

View More Projects

Interested in learning more about how GBA can assist with your facility objectives? Our portfolio is a great place to start. 

Skyscraper board room

430 N. Michigan (Realtor Building)

A large-scale vertical expansion called on GBA's analytical, design, and commissioning skills.

Hallway with rehab equipment

Shirley Ryan AbilityLab, Pediatric & DayRehab Center

This outpatient center serves children and adults; GBA provided engineering design services for the adaptive reuse project.

Exterior of Todd Building, University of Kentucky

University of Kentucky, Lee T. Todd, Jr. Building

An ASHRAE Level 1 audit,  retro-commissioning, and a lab ventilation assessment improved sustainability.